SPECIAL EVENTS AND TEMPORARY STRUCTURES APPLICATION FORM
This is the only form that is needed to apply for approval to erect temporary structures. Unless it is completed in full, the application will not be accepted.
Once all building work has been properly completed, the owner, contractor or builder may apply to the department for a Certificate of Occupancy. This must be issued by the department within 14 days of receiving the request, on condition that the work has been completed according to the approved plans. If the request is denied, the department must give reasons for its refusal. The building may only be used and occupied after a Certificate of Occupancy has been issued.
SANS 10400 – A Form 3 only to be used when the appointed person appoints a competent person to undertake the design of an element or segment of the building
When submitting a building plan application, scrutiny fees will be calculated according to official tariffs. These fees must be paid in full on submission of the application and are not refundable if the application is refused.